Black Mountain Irrigation District Capital Projects

 
(Water Treatment Plant)

Project 1 – Water Treatment Project

The objective of the water treatment project is to reduce suspended solids, color and total organic carbon levels in the water which will in turn reduce THM levels. The water treatment goal for turbidity is to meet the MAC of 1.0 NTU throughout the year. The goal for color is to meet aesthetic objective (AO) of 15 TCU at all times of the year with the average less than 5 TCU.

 

 

Of the chemicals tested, alum produced the best results, falling within acceptable levels for residual aluminum, and lowering turbidity significantly. From the pilot project, the demand for Chlorine was approximately half of raw settled water. The proposed location for the treatment facility is confirmed to be upstream of Stevens Reservoir where the system can operate by gravity.

 

Project 2 - Lower Garner Road

This improvement project provides the District with a second connection to PZ 553 and strengthens the watermain grid in the lower zone.

This connection lessens the possibility of stagnant water forming in the stub lines, particularly during low times in the winter.

Flow capacity is improved to the lowest zone in the Belgo area.

It allows for servicing around and isolation of PRV 7.

Because of the steep slope along the west side of Belgo Road, additional watermain would likely be required as the connection would be 100 meters north of the intersection.

 

Project 3 - Teasdale Road

This improvement project strengthens the District’s grid in the lower area of the Belgo water system.

This connection lessens the possibility of stagnant water forming in the stub lines, particularly during low times in the winter and provides an alternate feed when required. This improvement work affects only a small portion of the District.

 

Project 4 - PRV 7 Upgrading

This improvement project allows the District to properly service PRV 7. Presently there is only one line feeding the majority of the Belgo area. This line splits at PRV 7 into two areas. Presently there is a problem with the existing butterfly valve at the station and no means of isolating the water system nearby upstream.

Peak velocities through the larger 10" PRV are estimated at 15.9 feet/second which is high and marginally acceptable. Peak velocities through the smaller 6" PRV are estimated at 13.6 feet/second.

Approximately 200 cubic meters of water will have to be safely discharged when shutting down the water system. Fittings for the water system are a significant cost. Two 20" butterfly valves, one to replace the defective one in the station and a second to install near the feed to upper Garner Road, will be required. Also needed will be concrete cylinder pipe fittings and saw cutting of the concrete cylinder pipe.

 

Project 5 - PRV 1 Upgrading

This project involves the installation of a larger valve in the station complete with bypass piping. A flow meter is recommended in this location as this is a key monitoring location in the District.

Work would have to be performed in the off peak times, and is much easier now that the Wallace Road main is installed. Construction work is recommended to be scheduled in the late fall.

Peak summer flow through the 12" valve, with the Wallace Road PRV on-line taking 1400 Usgpm, is estimated to be 7500 Usgpm. This equates to a peak water velocity through the valve of 21 feet/second. Accounting for the possibility of additional development in the Rutland flatlands and along Highway 97, the future peak flows could be as high as 14000 Usgpm. The large valve size should be in the range of 500mm diameter. Alternately two 12" PRV’s could be used but would not fit within the existing vault.

This work will benefit all new development in the Rutland area and along Highway 97, and the existing water users. Costs have been split apportioned on water demand as new development will determine the timing for when the upgrade will be necessary.

 

Project 6 - Booster Station No. 1 Improvements

In accordance with FUS fire protection guidelines, either reservoir storage or standby power is required for areas serviced by a booster station. The existing station boosts the water from 90 psi to 132 psi. Even with a power failure, the majority of the service area has water except at the highest elevations. To provide emergency supply to this service area, three options exist:

    1. Upgrade the booster station to provide standby power in times of a power outage;
    2. Upgrade the pump station and install a new reservoir at the 665m elevation to provide emergency supply, or;
    3. Wait for development to occur on the surrounding hills and provide emergency supply from storage from the new development areas.

The booster station improvements were to provide additional water supply capacity so that development could proceed in the area surrounding the Black Mountain subdivision. The works designed in 1990 were to install a 100 hp and a 20 hp pump plus valves, meter and renovation to the existing building.

The work identified in this improvement project will benefit primarily new development. There will be some benefit to the existing users in the Black Mountain subdivision. Costs have been split apportioned on benefit.

 

Project 7 - Highway 97 Improvements

This work provides interconnection of the western limits of the distribution system. Three separate projects are identified as part of the Highway 97 water system improvements. These include:

    1. Connection on the west side between Stremmel and Willow Park Road (930 meters);
    2. Connection on the west side between Leathead and Fenwqick (1050 meters).

Benefits of this work are new development on the west side of the Highway. It is foreseen that this work will develop on a piecemeal basis as new areas come into the District and require water.

 

Project 8 - Campion Road Interconnection

It is estimated that there is limited fire protection at the limits of Campion Road. The system capacity can supply fire protection in the range of 2200 Usgpm with adequate residual pressure. To supply the District criteria of 2500 Usgpm, this connection will be required.

The benefits of this work are both new and existing development in the industrial subdivision.

 

Project 9 - Upper Wallace Road

This improvement project provides the District with a second connection to the Rutland flats area from the higher pressure zone. System supply capacity is improved. A second connection would be provided to both the 512 meter and 475 meter pressure zones.

This project will result primarily from new development and the majority of the cost will be paid by development, either by CEC contributions or installation by developers.

Benefits of this work are primarily new development. The only benefit to existing users is of a secondary feed to the lower zone.

 

Project 10 - Scotty Creek Road Improvements

Concerns exist with the supply of water from the Scotty Creek intake including chlorine contact time, exposure to low level runoff in the watershed, and quick changes in the raw water quality. The source is excellent for irrigation purposes and should continue to be used as such. This source however, has a higher risk than other District raw water sources.

In terms of domestic use, there are approximately 21 single family residences and two trailer parks totaling 230 domestic units in the Scotty Creek area. Converting the majority of these domestic connections to either the wells in the area or to the Mission Creek source is an option for this project.

Consideration was given to converting the entire water system onto the Mission Creek source but was ruled out as the majority of capacity is for irrigation and is already in place and this would be a large capital expenditure that would duplicate what is already in place.

Two options exist, 1) extend watermains to the area; or 2) convert trailer parks over and use point of use treatment for the remainder.

 

Project 11 - Supply Conduit Drainage

The location of this main supply conduit is high on the silt bluffs above Mission Creek between the tunnel and the lower settling basin. As such, it is exposed to the possibility of washouts or slope failures along the hillside. It is recommended that BMID take steps to minimize the slope failures or washouts to what can reasonably be foreseen. A failure during a time of high summer demand could result in severe economic loss to the District. The District must take all reasonable steps to secure their main source of supply.

A detailed assessment of flows was carried out for gullies flowing across the supply conduit. The proposed project involves the improvement of culvert inlet capacities, installation of culverts in major drainage channels and clean up of certain works. This project has high benefit to existing users and has relatively low capital costs.

 

Project 12 - Scada to Upper Watershed

This project allows for the control of release from the larger upper level storage facilities on BMID in the Mission Creek watershed. The largest storage reservoirs are Ideal Lake (5500 ac-ft), Graystoke Lake (3650 ac-ft) and Fish Hawk Lake (1500 ac-ft). Monitoring should be developed at the two largest sites. In most years, access is difficult in the early spring when the reservoirs are filling.

Flow measurement will be required from the release point from the dams, motorized control of the control valve/gate, transmitting and receiving capability, and a power source to operate the aforementioned.

 

Project 13 - Black Mountain Reservoir

As the primary supply conduit from Mission Creek approaches capacity of 40000 Usgpm, there will be a need for lower level storage. The reasons and beenfits of this reservoir are presented in detail in the Briefing report prepared for the District in 1995.

This work benefits the new development and to a lesser extent the existing users. It is also a project of significant magnitude that one developer would not be able to cover a significant portions of the cost of these works.

 

Project 14 - Reservoir Disaffection Facilities

During the construction of Black Mountain Reservoir, new disinfection facilities must be installed. In the Briefing report, order of magnitude costs for ozonation, chlorination and chloramination facilities were presented for comparison purposes. Two facilities were priced out, one at the north and one at the south end of the reservoir. In review of the concepts, it will be more likely be more feasible to install one disinfection facility at the south dam and additional piping from the south dam back through the south dam, across the reservoir floor to the north dam conduit.

 

Project 15 - East Bench Trunk Main

This improvement project provides the District with a feed from the future Black mountain Reservoir to the north end of the District and reduces velocities in the existing 36" diameter trunk main. The scope of work would be from the discharge from the new reservoir to the top of Swainson Road.

This work benefits primarily new development along the Rutland bench and flatlands.

 

Project 16 - Tower Ranch Supply

This includes work from Swainson Road above Booster Station No. 2 to the limits of the Tower Ranch site. As a result of the hydraulic analysis carried out in this study, the main size from Swainson northwards can be reduced from a 900 mm to 750 diameter. This work benefits only the existing users in the Belgo area.

 

Project 17 - East Bench Trunk Main to Gibson Road

This project involves connection from the East Bench Trunk Main down an easement across McKenzie Road, through another easement to Gibson Road. This provides the majority of the water system with a second connection. Two PRV’s are required.

Timing of this project would be after Black Mountain Reservoir and Disinfection facilities, and the East bench trunk main are constructed. This work benefits primarily new development in the Rutland flats area.

 

Project 18 - Gibson Trunk main to North End

This project consists of increasing the flow capacity of watermains from the connection at the East Bench trunk main northwards to Old Vernon Road. The project will be necessary as development occurs in the Rutland flats area which will eventually restrict the water supply capacity to the Industrial lands in the northwest corner of the District. The installation of this main will be part of water supply to the northwest limits.

 

Project 19 - Old Vernon Road (North Segment)

Two options are presented here, one to feed domestic water from the Mission Creek water system, the second to provide point of use treatment to those users. With only an estimated 22 domestic connections fed from Scotty Creek not including the mobile home parks, the cost estimated is high on a per unit basis. This work benefits only the existing domestic residences in the Scotty Creek area that are fed from the Creek.

 

Project 20 - Old Vernon Road (West Segment)

This connection is dependent on the upstream connections being made above and along Gibson Road and up to the East Bench trunk main. The connection proposed would strengthen the watermain grid in the northwest industrial grid. This connection will also provide a possibility of three feeds to the Rutland flats area. Development in Rutland will have an adverse effect on the northwest limits of the water distribution system. This project will be development dependent and benefits the existing area and new development.

 

Project 21 - Northwest District Limits Supply

This is a development dependent project and involves the servicing of lands presently not within a Water District. These lands were identified in the KJWC report to fall within the BMID service area.

The estimated water demand for the area, should it decide to come into the district is 950 Usgpm. A 250 mm watermain would be required.

 

Project 22 - East Benchlands Supply

These works are development dependent. The land is at a high elevation and is presently within the ALR. Because of this, the present zoning, which restricts minimum lot sizes to 5 acre plots, development is not foreseen in the near future.

 

Project 23 - Mine Hill/Bell Mountain Development Supply

Extension of watermain onto these two higher areas of land is development dependent. Some of the land is in the ALR. Maximum daily demand to build-up is estimated to be in the range of 1200 Usgpm. A 250 mm watermain and booster station on one of the higher points of land would be required. Zones should be set up with pumping through one zone and backfeeding to that zone through PRV’s from above.

 

 

 

© 2002 www.bmid.org   All Rights Reserved.